The works in the Municipality of Varvarin are executed at multiple locations. In Obrež, works are executed at three locations while the location of Rosulje in Svrljig has been completed.

Four sites are currently active in the Municipality of Varvarin for which the “Clean Serbia” Project plans the total 44,738.63 meters of length of sewage network.

Active sites in the Municipality of Varvarin are in Obrež. Currently, the works are being executed in the following streets:
1. Ive Lole Ribara St.,
2. Branka Krsmanovića St.,
3. Veljka Vlahovića St.

After the completion of works at the location of Rosulje in Svrljig, the works are currently being executed in the 13. oktobar St. where the processing of manholes and preparation for watertightness testing are in progress.

Apart from the sewage network, the “Clean Serbia” Project plans for the construction of four wastewater treatment plants in the aforementioned municipality. The value of these designs is close to 22 million Euros.