In Kučevo, the work is already half done

10. October 2022.



Share this article

Share on facebook
Share on twitter
Share on linkedin

Works on the construction of sewage infrastructure in the Municipality of Kučevo have reached practically half. The streets are being prepared for asphalting.

The total projected length for two construction sites on the territory of the Municipality of Kučevo provided by the project is: PHASE 1 + PHASE 2 17,428.50 m. So far, a total of 6,295.50 meters have been constructed.

Preparations are underway for the execution of house connections, as well as preparations for asphalting the streets, which will practically complete the works at those locations.

The works carried out in Kučevo are worth 11 million euros, and are practically the largest infrastructural investments in this municipality. As previously announced, the work on the Rabrovo location should also begin this autumn.