NEWS

Dry autumn is favorable for works on project

16. November 2022.



Share this article

Share on facebook
Share on twitter
Share on linkedin

The good weather conditions this autumn enabled the work on the implementation of the “Clean Serbia” project to proceed smoothly. In the past month, a new kilometer of sewage network was built:

No Construction site The length now being worked in meters Total length meters Note

(if necessary)

1. Lajkovac 0,00 8.622,16
2. Knić 4027.09 34,390.80
3. Kragujevac 10375.40 41,745.42
4. Krupanj 0,00 1.611,60
5. Kladovo BrzaPalanka L= 102m

 

Rit L= 395m

BrzaPalanka L= 2.185m od 2.287m pougovoru.

 

Rit L= 1.777m od 2.984m pougovoru.

 

6. Lazarevac 953,00 12.450,52
7. Mionica 369,00 2.198,47
8. Obrenovac 677,97 12.645,41
9. Svrljig The total length of the currently running sections:

953,5

Total length of open sections: 2409,20 length per annex:

6040m

10. Varvarin 12900,25 35768,14 44739m
11. Vranje 2286 8708,07 141675m
12. Kučevo Faza I L= 466m

 

Faza II L= 568m

Faza I L= 5.185m od 7.115m pougovoru.

 

Faza II L= 3.352,50m od 10.313,50m pougovoru.

 

13. Novi Sad 1.895,33 26.683,56
14. Novi Bečej 1.204,06 38.280,12
15. Banja Vrujci 0,00 3.522,67
16. VelikiCrljeni 862,00 7.098,90