NEWS

Sewer network for more than 3000 households in Kisač and Čenej

30. October 2022.



Share this article

Share on facebook
Share on twitter
Share on linkedin

Works at the Kisač and Čenej locations in Novi Sad are progressing according to the expected dynamics. The construction site in Čenej is practically completed.

The implementation of the project in the settlement of Čenej will enable connection to the sewage network for 715 households. On this construction site, 14,487.54 meters have already been built and the gravity sewer network is almost completely completed. As stated in the “Clean Serbia” regional center in Novi Sad, it remains for the investor answers to the inquiry sent to him at the beginning of the year regarding the implementation of the secondary network.

In Čenej, work is currently being carried out on the pumping stations, which started after the electrical installations were moved, which made it impossible to carry out the work safely.

Of the contracted 66,800.00 m of sewage network in the municipality of Novi Sad, 12,077.98 m was constructed in Kisač. After obtaining the approval for asphalting by the road supervision, almost all the sections on which the works were separated were returned to their original condition, according to the conditions stipulated in the contract. Preparatory works at the pumping stations have been completed, and after receiving approval from the supervisory authority, their execution will begin.

The “Clean Serbia” project envisages the construction of 2 pumping stations, and as many as 2,371 individual households will be connected to the sewage system. The works carried out in Kisač and Čenej are worth 2 billion dinars.