As many as four villages in the Municipality of Svilajnac will receive through the “Clean Serbia” project sewage network. The works are taking place according to the expected dynamics.
Troponje, Kusiljevo, Subotica and Sedlare are the four villages of Svilajnac Municipality where works on the construction of the sewage network are underway.
In Kusilje, the construction of 31,513m of gravity sewerage and 940.5m of pressure sewerage was planned, of which 21,691m of gravity and 533m of pressure sewerage were completed by the first week of July.
In the village of Sedlare, the project envisages the construction of 10,590 m of gravity sewerage and 1,558m of pressure sewerage. The works were carried out in a length of 8,303 m of gravity and 684 m of pressure sewers.
In the village of Subotica, the implementation of the “Clean Serbia” project envisages the construction of 10,666 m of gravity sewerage, and 8,972 m have been constructed so far.
In the village of Troponje, the project foresees 16,638 m of gravity sewerage and 230 m of pressure sewerage, of which 9,926m of gravity sewerage has been completed.
The mentioned works are taking place within the first phase of the project, the value of which is around 30 million euros. The second phase of this project includes the villages of Grabovac, Crkvenac, Dublje, part of Svilajnec and the construction of a wastewater treatment plant.
When the entire project is finished, about 70 percent of the citizens of the municipality of Svilajnac will have regulated sewage.