Works within the ‘Clean Serbia’ Project are progressing

Rainy September did not reduce the scope of works within the ‘Clean Serbia’ Project. New dozens of sewage network meters have been executed in each of the cities and municipalities in which the Project is being implemented while on the other hand September marked the finish of works on certain locations. During the previous month designing of new routes of sewage infrastructure begun so that new sites could be opened as soon as spring begins.

SN. Site What is being executed Length executed in meters Total length in meters Note

(if necessary)

1. Lajkovac Sewage 587.00 8,594.99  
2. Knić Sewage 3142.30 m 34390.80  
3. Kragujevac Sewage 8720.60 m 41745.42  
4. Krupanj Sewage 0.00 1,611.60  
5. Kladovo Sewage Brza Palanka 1123m

Rit 796m

5271m Correction of sewage network is being done in Rtkovo
6. Lazarevac Sewage 967.00 11,510.43  
7. Mionica Sewage 649.00 1,829.47  
8. Obrenovac Sewage 157.34 11,967.44  
9. Svrljig Sewage 1212.90 2072.20 Length according to the Annex 6040m
10. Varvarin Sewage 9686.95 27041 44739m
11. Vranje Sewage 5785.45 11698.07 141675m
12. Kučevo Sewage Kučevo phase I 313m

Kučevo phase II 1428m

17,428.50m  
13. Novi Sad Sewage 26683.56 42,072.51 2 aktivna gradilišta

 

14. Novi Bečej Sewage 38280.48 46,535.25 2 aktivna gradilišta.

 

15. Banja Vrujci Sewage 0.00 3,595.86  
16. Veliki Crljeni Sewage 799.00 6,236.90