Another 8.6 km of sewage network in Obrenovac

In the Municipality of Obrenovac, works are nearing completion on three construction sites in the settlements of Zvečka, Urovci and Krtinska Street.

Out of the total projected length of 5,988.64 meters in the Zvečka settlement, works have already been carried out in a length of 4375.89 m. At the same time, works on the construction of the sewage network in Urovci and Krtnska street were carried out in a length of 4375.89 m from the total projected length 5988.64 meters.

In the “Clean Serbia” Regional Center, they state that work is currently being carried out on the construction of outlets for household connections, as well as on the construction of low-pressure sewage.

The aforementioned works were preceded by the construction of a 40 km sewerage network in the settlements: Šljivica, Belo Polje, Braće Jugović settlement, in the direction of Valjevo and Ubu.

The implementation of the “Clean Serbia” project envisages the construction of two wastewater treatment plants in Obrenovac.