Đurić: Works in Čenej to be finished by the end of august

The Mayor of Novi Sad Milan Đurić while visiting the site of works in Čenej, town where the works within the “Clean Serbia” Project are being executed, announced that the works will be finished in August.

Đurić said that within the “Clean Serbia” Project, planned surface to be covered with sewage is 17.5 kilometers, and the value of works is 840 million Dinars.

“We have invested 1.6 billion Dinars in Čenej in the last decade, and we will continue to do so. The implementation of the “Clean Serbia” Project is of immense value for that town, and includes construction of around 17.5 kilometers of sewage network and three pumping stations in the total value of 840 million Dinars. The works are progressing smoothly, and currently, the Contractor is at about 83% of total completion of the works”, Đurić said.

In the previous period, roads with public lighting have been built in the Ratarska Street, worth 50 million Dinars, then in the Nova Street, worth 29 million Dinars, and design and technical documentation has been prepared for the construction of traffic facilities in the Relje Savić Street. Additionally, at the request of citizens, a playground for children has been placed, for which 3 million Dinars have been allocated.

“Additionally, three pumping stations and a wastewater purifier are planned for construction, which will cost 240 million Dinars. We expect that Čenej will be fully done by the end of August, as far as sewage is concerned. A new playground for children has also been built, in the value of three million Dinars”, Đurić emphasized.

Sewer network for more than 3000 households in Kisač and Čenej

Works at the Kisač and Čenej locations in Novi Sad are progressing according to the expected dynamics. The construction site in Čenej is practically completed.

The implementation of the project in the settlement of Čenej will enable connection to the sewage network for 715 households. On this construction site, 14,487.54 meters have already been built and the gravity sewer network is almost completely completed. As stated in the “Clean Serbia” regional center in Novi Sad, it remains for the investor answers to the inquiry sent to him at the beginning of the year regarding the implementation of the secondary network.

In Čenej, work is currently being carried out on the pumping stations, which started after the electrical installations were moved, which made it impossible to carry out the work safely.

Of the contracted 66,800.00 m of sewage network in the municipality of Novi Sad, 12,077.98 m was constructed in Kisač. After obtaining the approval for asphalting by the road supervision, almost all the sections on which the works were separated were returned to their original condition, according to the conditions stipulated in the contract. Preparatory works at the pumping stations have been completed, and after receiving approval from the supervisory authority, their execution will begin.

The “Clean Serbia” project envisages the construction of 2 pumping stations, and as many as 2,371 individual households will be connected to the sewage system. The works carried out in Kisač and Čenej are worth 2 billion dinars.

Mayor of Novi Sad Milos Vucevic in visit of works in Cenej

On Sunday, March 27, the works on the construction of fecal sewage network in Cenej were visited by the Mayor of Novi Sad Milos Vucevic and the representatives of the Regional Center of the China Road and Bridge Corporation (CRBC).

“Over two billion RSD is being invested in sewage in Cenej and Kisac. Addressing those municipal problems will bring those two villages up to the development rank of villages in Austria, Hungary and Slovakia”, the Mayor of Novi Sad, Milos Vucevic, has stated.

In the Settlement of Cenej, Municipality of Novi Sad, more than 13.5 of fecal sewage network has been constructed so far, and a total of 17,498 meters of network as well as a contemporary wastewater treatment plant is planned for construction.