In Kladovo, works are nearing completion, followed by WWTP

A presentation of the “Clean Serbia” project was held in Kladovo, which was attended by representatives of the local self-government and the CRBC company. Through the “Clean Serbia” project, this municipality will receive 40.6 km of sewage network and even two wastewater treatment plants.

As stated at the presentation in Kladovo, works on six locations in this municipality within the “Clean Serbia” project are coming to an end.

“The work on the missing sewage network is progressing. There are still two kilometers left to be completely completed, and we also have two wastewater treatment plants in Podvrška and Kostol. The plant in Kostol, with a capacity for 15,000 inhabitants, meets the needs of Kladovo and parts of Kostol,” said Marija Jocić, leading engineer of the waste water treatment plant design of the “Clean Serbia” project.

During the presentation, the importance of the construction of the mentioned facilities in order to preserve the environment, but also the fact that Serbia should be aligned with the EU directive on its way to Europe, was emphasized on several occasions.

“Kladovo flows onto the Danube River, which is protected by the Danube Convention, and we have to comply with the capacity and parameters of the water before we discharge it into the receiver, which in this case is the river.” For the local population, this is an important step, it will improve the quality of life. Until now, all sewage in this part has been discharged directly into the river, and with the construction of the plant, it will be treated to a level that does not endanger the environment or the health of people in this region,” Jocić pointed out.

The “Clean Serbia” project is important for Kladovo

The “Clean Serbia” project in Kladovo is coming to an end. “This capital project will mean the most for the accelerated development of tourism in the municipality of Kladovo, a new and major tourist destination in Serbia,” Borske narodne novine reports.

Through the implementation of the “Clean Serbia” project, Kladovo gets 41 km of sewage network, which includes part of Brza Palanka, Velika Vrbica, Rtkovo and Korbovo. Borska narodne novine also reminds that the new sewage system is arriving in the village of Pdrvška in a length of 13 km, while wastewater treatment plants are planned in Kostol and POdvrška.

The investment in Kladovo is worth 21.3 million euros, which makes this project one of the key and capital projects for the development of Kladovo.

 

“Clean Serbia” for the protection of the Mali Pek river

As part of the “Clean Serbia” project, in addition to the sewage network, a wastewater treatment plant (WWTP) will be built in Kladovo. The implementation of this project will protect the river Mali Pek.

In the municipality of Kladovo, waste water is directly poured into the Mali Pek river, which damages the biodiversity of the area.

The “Clean Serbia” project envisages that waste water will be transported to a processing plant that will be built not far from the city, near the former Veliki Srebra, Zlatara Majdanpek plant. The value of these works is slightly less than nine million euros.

The construction of the sewage network will cover the following settlements, villages and parts of the Kladovo municipality: Velika Vrbica – 7,788.48 m, Rtkovo – 6,471.66 m, Korbovo 7,675.98 m, Rit – 2,984.00 m, Brza Palanka – 2,287.00 m and Podvrška – 13,393.15 m.

Kladovo: In several locations, works are nearing completion

By the end of October, works are expected to be completed at several locations in the Municipality of Kladovo. Velika Vrbica, Rtkovo, Brza Palanka, Rit are locations where communal infrastructure is being built as part of the “Clean Serbia” project.

As part of the “Clean Serbia” project, work continues on the excavation and installation of fecal sewage pipes at the construction site in Velika Vrbica, Municipality of Kladovo. The total projected length is 7,888.4 m. So far, 2,095.3 meters have been constructed and preparations for asphalting the streets are underway.

At the construction site in Korbovo, Kladovo, in the same municipality, 1,920.24 meters of the total projected length of 7,675.99 meters have been constructed so far. Preparations for asphalting streets under asphalt are underway.

In the same municipality, intensive works are also being carried out in Rtkov, where the works are in the final phase in a length of 473.38 m out of the total projected length of 6,471.66 m. Completion of works on the construction of fecal sewage is also expected in Brza Palanka, where the works started in August of this year and where 1,176.00 meters of the planned 2,287.00 meters have already been completed. The expected completion of the works is October 30, 2022.

Works on the construction of fecal sewage in Rit settlement in Kladovo municipality also started in mid-August and already 1,176.00 meters of the projected 2,984.00 meters have been constructed. The expected completion of the works is also at the end of October.

The “Clean Serbia” project envisages the construction of 41 kilometers of sewage network in Kladovo and two waste water treatment plants in the suburban settlement of Kostol and in the MZ Podvrška.

Minister Momirovic visiting the works in Kladovo

The Minister of Construction, Transport and Infrastructure Tomislav Momirovic has visited with his associates the works on construction of sewage infrastructure in Kladovo which are being implemented within the scope of the “Clean Serbia” Project.

The implementation of the “Clean Serbia” Project in Kladovo began in November of last year, and the works are carried out by the companies CRBC and PIM Belgrade.

The Minister reminded that 41 km of sewage network and two wastewater treatment plants will be constructed on the territory of the Municipality of Kladovo: in Kladovo and in the settlement of Podvrska. ‘The “Clean Serbia” Project is a contribution by the state to all Local Self-Governments of Serbia with the goal of systematic solution of all ecology-related problems. That is why all of this that we do can also be perceived from the aspect of even regional development. Our goal is to protect the environment, our rivers, mountains, for the future generations and to improve the living conditions of every single resident,’ said the Minister.

The works are currently being executed on three construction sites, and have been intensified with the more favorable weather conditions:

KORBOVO (completed works): Pipes DN 200 -100m, Pipes 250 – 1.303 m, Manholes – 44 placed.

VELIKA VRBICA (completed works): Pipes DN 250 – 1,158 m, Pipes DN 200 – 514 meters, Manholes –  68 placed.

RTKOVO (completed works): Pipes DN 250 – 271m, Manholes – 13 placed.

Total value of the “Clean Serbia” Project in the Municipality of Kladovo is 21,306,281 EUR.