Sewage infrastructure kilometers for July

Warm weather in July has facilitated the intensity of works within the  ‘Clean Serbia’ Project. New kilometers of sewage network were realized in accordance with the planned schedule.

SN. Site Executed length  (meters) Total length (meters) Note

 

1. Lajkovac 454.44 4.628,14  
2. Knić 2,457.00 34,390.80  
3. Kragujevac 7,057.80 41,745.42  
4. Krupanj 0 847.83  
5. Kladovo Rtkovo-0m

Velika Vrbica-0m

Korbovo-0m

22 219.72 m Revision of sewage network currently in progress in Rtkovo
6. Lazarevac 0 8,838.79  
7. Mionica 141.31 710.05  
8. Obrenovac 882.83 9,175.93  
9. Svrljig 700m 6040m 700m
10. Varvarin 6762m 44738m 6762m
11. Vranje 3563m 141675m 3563m
12. Kučevo Kučevo Phase I-700m

 

7115m  
13. Novi Sad 24,393.00 42,072.51 2 active sites with two construction permits, Kisač and

Čenej.

14. Novi Bečej 35.996,83 46,535.25 3 active sites with 3

construction permits.

15. Banja Vrujci 820.27 3,595.86  
16. Veliki Crljeni 226.31 2,007.00