Preparation for asphalting at three locations in Lajkovac

As part of the “Clean Serbia” project, works are slowly coming to an end at as many as three locations.

So far, 2869.91 m of sewage network has been built in the Municipal Municipality of Rubribreza. works have been carried out to restore the roadway to its original state, and works on the handover of the building are to come. Works are nearing completion in Jabučje, where the total projected length is 4041.93m. so far completed 4014.13 m of sewage network.

On the third construction site in the Municipality of Lajkovac, the works on the construction of fecal sewerage in the settlement of Bogovađa are coming to an end, where 1738.14 m of the total projected length of 1745.0 m have been constructed. While the finishing works are in progress, the ground is being prepared for restoration and asphalt works.

How important the implementation of the “Clean Serbia” project is for the Municipality of Lajkovac is also evidenced by the fact that in Jabuče alone, around 2,000 households will receive a new sewage network.

Commencement of works in Bogovađa near Lajkovac

After the completion of sewage network for a part of Rubibreza in the near vicinity of the Municipality of Lajkovac, construction of two kilometers of sewage network has commenced in Bogovadja. The ‘Clean Serbia’ Project also plans for the construction of a wastewater treatment plant.

The construction of two kilometers of primary sewage network has commenced in Bogovađa. The president of the Municipality of Lajkovac Andrija Živkovic has attended the start of works and took the chance to emphasise that the implementation of the “Clean Serbia” Project one of the most significant projects in the Municipality of Lajkovac.

“The value of works is around 2 billion Serbian Denars which is more than two annual municipal budgets. We have already completed Phase I – sewage for a part of Rubibreza and this local community is now completely covered by wastewater sewage. Works are well underway in the LC of Jabucje where Phase I has been completed and Phase II should begin soon: where in the second part of Jabucje 24 kilometers of primary network will be constructed. The Municipality of Lajkovac will, in the following period, in accordance with budget possibilities and technical conditions, construct sewage for parts of Bogovađa distant from the center, but with these two kilometers most of the settlement of Bogovađa is covered. Thanks to good cooperation with the Ministry of Construction, there is a good chance that we will receive four kilometers of primary sewage for the settlement of Ćelije, in the value of 50 million Serbian Denars, even though at first that was not part of the ‘Clean Serbia’ Project plan. By the end of August, complete reconstruction of the existing wastewater treatment plant in Lajkovac will begin, which will be able to accept new users, and the sewage in Jabučje and Ćelije will be connected to this plant” Živkovic stated.

Wastewater treatment plant will have the capacity for 600 users, which enables the further expansion of the network.

 

 

Živković: Lajkovac and the surrounding villages will be covered by a sewage network

President of the Municipality of Lajkovac, Andrija Živković has highlighted that the “Clean Serbia“ Project is one of the most important projects in this Municipality in the last few decades. The works in this Municipality have reached Phase two, and currently, the works are being carried out on the construction of a sewage network in Jabučje.

“Last year, we have started Phase one of the Project, completed Rubibreza where 4km of sewage network was constructed, and a few days ago the works on Phase two of the Clean Serbia Project have begun on a sewage network which will cover our most populated place after Lajkovac, the Local Community of Jabučje, where 26 km of primary sewage network will be built, however in the center of the village secondary sewage will be constructed for vital facilities located in the center of Jabučje, as well as for several hamlets like Negić, roundabout for Tomići“, says Živković .

He has stated that on the very section five pumping stations will be constructed for the purposes of the sewage networl. The plan is that the entire sewage network gets connected to the pumping station Borverk, which Lajkovac has constructed independently a few years ago. “From there, later on, it will go towards a wastewater treatment plant which is on the border of Lajkovac and Ćelije and which has entered this Project and will be completely re-constructed and operational soon. The next phase, the start of which we are expecting, is the construction of the primary sewage network and construction of a brand-new plant in Bogovađa. This Project is important for the whole of Jabučje because of how it raises the economic awareness of the residents and with this Project, all locals will get the possibility of connecting to a sewage network, becase it is the 21st Century and that is necessary for living“, says Živković.

With the implementation of the “Clean Serbia“ Project, more than 3000 residents of the settlement of Jabučje and around 2000 households will receive a sewage network. Živković has stated that he expects the works to last for the remainder of the year and to be completed with the start of 2023.

“All hamlets of Jabučje from Viš, Staro selo, Donji kraj, Gornji kraj, Gaj to Serinka will be covered by a primary sewage network. A big thank you to the Government of the Republic of Serbia, the Ministry of Construction and its Minister Tomislav Momirović for recognizing the importance of the Project and Lajkovac being among first cities and municipalities to enter this Project and I hope that in the future we will have more good news regarding our municipalities. With the construction of this network, roads will be renewed on the territories where the sewage will be constructed, which will restore them to their original condition. That means that apart from the sewage network, road infrastructure will be upgraded as well and I expect the works to progress according to the planned dynamics“, says the president of the Municipality emphasizing that with the implementation of the “Clean Serbia“ Project, Lajkovac and its surrounding villages will bee 100% covered by a sewage network.

Construction season starts in Lajkovac with “Clean Serbia”

The president of the Municipality of Lajkovac, Andrija Zivkovic, while announcing the construction season which is supposed to start sometime this week in Lajkovac, has put a special emphasis on the works which are in the scope of the “Clean Serbia” Project.

At the Council meeting in the Municipality of Lajkovac, the president of the Municipality of Lajkovac, Andrija Zivkovic has announced the phase two of the “Clean Serbia” Project.

“In the first phase of this Project, a sewage network has been constructed in Rubibreza, the second phase is the construction of the sewage and complete reconstruction of the wastewater treatment plant in Lajkovac. I hope that, in the following moths, the third phase of works will also start and those include, apart from the construction of the sewage network, the construction of a brand new wastewater treatment plant in Bogovadja”, says the President of the Municipality of Lajkovac.

The total length of the sewage network which will be constructed in Lajkovac is 30,193.93 meters.