Works within the “Clean Serbia” project in Kragujevac are currently being carried out at the Petrovac and Veliko polje – Grošnica locations. The works were completed in Dimitrija Katić and Sveta Pavlović Streets.
In the settlement of Petrovac in Kragujevac, works are underway on the construction of a 3,920 m long sewage network, where as many as 125 manholes and 250 cisterns will be installed. So far, works have been carried out in Djurdja Branković Street for a length of 100 meters and work has begun in Kikindska street.
In the settlement of Grošnica, the “Clean Serbia” project envisages the construction of 3,139 meters. Work has begun on the installation of the sewage network in Kučajska street, where 90 meters have already been completed, and the project envisages the installation of 115 manholes and pipes of the fi250 profile.
That the implementation of the project in Kragujevac is progressing is also evidenced by the fact that after the completion of the works on laying the pipes in Bogoljuba Djurdjevića Street in the upper part, technical tests are underway, while the works in the same street in its lower part have already started.