The construction of the secondary sewage network in Veliki Crljeni is underway

As part of the “Clean Serbia” project, 52,597.59 meters of sewage network will be built in the Veliki Crljeni settlement.

Works on the construction of fecal secondary sewerage in Veliki Crljeni are proceeding according to the expected dynamics, so 4,600.0 m have been completed so far.

Currently, installation works and works on the preparation of the terrain are being carried out to restore it to its original state.

In addition to the sewage network, the “Clean Serbia” project in Veliki Crljeni also envisages the construction of a wastewater treatment plant that will cover 20,000 inhabitants.

Preparation for asphalting at three locations in Lajkovac

As part of the “Clean Serbia” project, works are slowly coming to an end at as many as three locations.

So far, 2869.91 m of sewage network has been built in the Municipal Municipality of Rubribreza. works have been carried out to restore the roadway to its original state, and works on the handover of the building are to come. Works are nearing completion in Jabučje, where the total projected length is 4041.93m. so far completed 4014.13 m of sewage network.

On the third construction site in the Municipality of Lajkovac, the works on the construction of fecal sewerage in the settlement of Bogovađa are coming to an end, where 1738.14 m of the total projected length of 1745.0 m have been constructed. While the finishing works are in progress, the ground is being prepared for restoration and asphalt works.

How important the implementation of the “Clean Serbia” project is for the Municipality of Lajkovac is also evidenced by the fact that in Jabuče alone, around 2,000 households will receive a new sewage network.

Another 8.6 km of sewage network in Obrenovac

In the Municipality of Obrenovac, works are nearing completion on three construction sites in the settlements of Zvečka, Urovci and Krtinska Street.

Out of the total projected length of 5,988.64 meters in the Zvečka settlement, works have already been carried out in a length of 4375.89 m. At the same time, works on the construction of the sewage network in Urovci and Krtnska street were carried out in a length of 4375.89 m from the total projected length 5988.64 meters.

In the “Clean Serbia” Regional Center, they state that work is currently being carried out on the construction of outlets for household connections, as well as on the construction of low-pressure sewage.

The aforementioned works were preceded by the construction of a 40 km sewerage network in the settlements: Šljivica, Belo Polje, Braće Jugović settlement, in the direction of Valjevo and Ubu.

The implementation of the “Clean Serbia” project envisages the construction of two wastewater treatment plants in Obrenovac.